CHEESE ROPE ROOMS

Ornua Cheese rope rooms 8.jfif

CLIENT REQUIREMENTS

We were asked by our client to convert a part of their warehouse into a full high care food production room, with an automated boxing and bagging system capable of handling 1 ton of cheese ropes per hour.

OUR SOLUTION

Considering the very tight time frame and budget given on the project we proposed all work be done in house by us. This included all ground works, electrical installations, pipe work, flooring, wall and roof install and plant install.

 

The site was run under full CDM regulations by M&J from start to finish as part of a larger upgrade to the factory and the cheese rope rooms achieved a triple A hygiene rating after the installation. 

Ornua Cheese rope rooms 7.jfif
Ornua Cheese rope rooms 6.jfif

KEY SPECIFICATIONS

  • Full CDM Site managed by M&J Europe

  • Full Project Management from design stage to completion

  • Full production integration from in feed to out feed